In construction projects, when one-program costs more than planned, decision makers are forced to delay or cancel other activity. Value Engineering can play a key role in overcoming such problems by ensuring programs stay within project duration, estimated budget and saving costs. This study was conducted to assess the applicability of value engineering concept and the current management practice of Ethiopian building construction projects. In this study, knowhow of Ethiopian building construction project experts on value engineering principles were studied and the current management practice was examined. In order to gather required information, questionnaire, interview with project managers and archival review was conducted. Data was analyzed both qualitatively and quantitatively. The result of this study shows, main challenges in the project area were: delay in progress payment by owner, poor site management, weak follow up by consultant, and delay in material delivery from contractor side. Almost all experts in the project have no knowledge on the principle of value engineering and has no willingness to implement the principle. The evaluation made using value engineering principle shows the current management practice was more conventional and the industry is still facing delay of projects, cost overrun and poor quality while there are opportunities to minimize such problems.
Published in | American Journal of Civil Engineering (Volume 7, Issue 1) |
DOI | 10.11648/j.ajce.20190701.11 |
Page(s) | 1-8 |
Creative Commons |
This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited. |
Copyright |
Copyright © The Author(s), 2019. Published by Science Publishing Group |
Building Construction, Ethiopian Construction, Project Management, Value Engineering
[1] | PMI Standards Committee, A guide to the Project Management Body of Knowledge [electronic version], Fifth. Atlanta, 2013. |
[2] | W. T. Chen, P. Y. Chang, and Y. H. Huang, “Assessing the overall performance of value engineering workshops for construction projects,” Int. J. Proj. Manag., vol. 28, no. 5, pp. 514–527, 2010. |
[3] | S. Swetha;, N. R. Smruthi;, and M. Aleem, “Application of Value Engineering in Building Construction,” Int. J. Adv. Res. Sci. Eng., vol. 5, no. 10, pp. 253–267, 2016. |
[4] | K. Ilayaraja and M. Zafar Eqyaabal, “Value Engineering in Construction,” Indian J. Sci. Technol., vol. 8, no. 32, pp. 3–10, 2015. |
[5] | A. Jaapar, “Value management study to the Malaysian construction industry,” BEAN 2008 Conf., no. Shen 1995, 2008. |
[6] | K. H. Allan Ashworth, Added Value in Design and Construction, Second. Newyork: Routledge, 2014. |
[7] | R. Rachwan, I. Abotaleb, and M. Elgazouli, “The Influence of Value Engineering and Sustainability Considerations on the Project Value,” Procedia Environ. Sci., vol. 34, pp. 431–438, 2016. |
[8] | U. A. Mahadik, “Value engineering for cost reduction and sustainability in construction projects,” J. Mech. Civ. Eng., vol. 1, no. NA, pp. 95–97, 2015. |
[9] | N. T. V Gowrisankar, N. Tom, and V. Gowrisankar, “VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION,” Int. J. Civ. Eng. Technol., vol. 6, no. 6, pp. 46–52, 2015. |
[10] | A. Sharma and R. M. Belokar, “Achieving Success through Value Engineering : A Case Study,” in Preceedings of the World Congress on Engineering and Computer Science, 2012, vol. II, pp. 24–27. |
[11] | K. Ali, A. Ahmed, and R. K. Pandey, “Concept of Value Engineering in Construction Industry,” Int. J. Sci. Res., vol. 5, no. 4, pp. 1231–1237, 2016. |
[12] | A. Hayter, Probability and Statistics for Engineers and Scientists, Fourth. Denver, 2012. |
[13] | S. Assefa, Z. T. Worke, and M. Mohammed, “Stakeholders Impact Analysis On Road Construction Project Management in Ethiopia : A Case Of Western Region,” vol. 0869, no. 11, pp. 115–121, 2015. |
[14] | O. O. Ugwu; I. C. Attah, “AN APPRAISAL OF CONSTRUCTION MANAGEMENT PRACTICE IN NIGERIA,” Niger. J. Technol., vol. 35, no. 4, pp. 754–760, 2016. |
APA Style
Tsigereda Garomsa, Elmer De Castro Agon, Sintayehu Assefa. (2019). Concept of Value Engineering and Current Project Management Practice in Ethiopian Building Construction Projects. American Journal of Civil Engineering, 7(1), 1-8. https://doi.org/10.11648/j.ajce.20190701.11
ACS Style
Tsigereda Garomsa; Elmer De Castro Agon; Sintayehu Assefa. Concept of Value Engineering and Current Project Management Practice in Ethiopian Building Construction Projects. Am. J. Civ. Eng. 2019, 7(1), 1-8. doi: 10.11648/j.ajce.20190701.11
AMA Style
Tsigereda Garomsa, Elmer De Castro Agon, Sintayehu Assefa. Concept of Value Engineering and Current Project Management Practice in Ethiopian Building Construction Projects. Am J Civ Eng. 2019;7(1):1-8. doi: 10.11648/j.ajce.20190701.11
@article{10.11648/j.ajce.20190701.11, author = {Tsigereda Garomsa and Elmer De Castro Agon and Sintayehu Assefa}, title = {Concept of Value Engineering and Current Project Management Practice in Ethiopian Building Construction Projects}, journal = {American Journal of Civil Engineering}, volume = {7}, number = {1}, pages = {1-8}, doi = {10.11648/j.ajce.20190701.11}, url = {https://doi.org/10.11648/j.ajce.20190701.11}, eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ajce.20190701.11}, abstract = {In construction projects, when one-program costs more than planned, decision makers are forced to delay or cancel other activity. Value Engineering can play a key role in overcoming such problems by ensuring programs stay within project duration, estimated budget and saving costs. This study was conducted to assess the applicability of value engineering concept and the current management practice of Ethiopian building construction projects. In this study, knowhow of Ethiopian building construction project experts on value engineering principles were studied and the current management practice was examined. In order to gather required information, questionnaire, interview with project managers and archival review was conducted. Data was analyzed both qualitatively and quantitatively. The result of this study shows, main challenges in the project area were: delay in progress payment by owner, poor site management, weak follow up by consultant, and delay in material delivery from contractor side. Almost all experts in the project have no knowledge on the principle of value engineering and has no willingness to implement the principle. The evaluation made using value engineering principle shows the current management practice was more conventional and the industry is still facing delay of projects, cost overrun and poor quality while there are opportunities to minimize such problems.}, year = {2019} }
TY - JOUR T1 - Concept of Value Engineering and Current Project Management Practice in Ethiopian Building Construction Projects AU - Tsigereda Garomsa AU - Elmer De Castro Agon AU - Sintayehu Assefa Y1 - 2019/02/27 PY - 2019 N1 - https://doi.org/10.11648/j.ajce.20190701.11 DO - 10.11648/j.ajce.20190701.11 T2 - American Journal of Civil Engineering JF - American Journal of Civil Engineering JO - American Journal of Civil Engineering SP - 1 EP - 8 PB - Science Publishing Group SN - 2330-8737 UR - https://doi.org/10.11648/j.ajce.20190701.11 AB - In construction projects, when one-program costs more than planned, decision makers are forced to delay or cancel other activity. Value Engineering can play a key role in overcoming such problems by ensuring programs stay within project duration, estimated budget and saving costs. This study was conducted to assess the applicability of value engineering concept and the current management practice of Ethiopian building construction projects. In this study, knowhow of Ethiopian building construction project experts on value engineering principles were studied and the current management practice was examined. In order to gather required information, questionnaire, interview with project managers and archival review was conducted. Data was analyzed both qualitatively and quantitatively. The result of this study shows, main challenges in the project area were: delay in progress payment by owner, poor site management, weak follow up by consultant, and delay in material delivery from contractor side. Almost all experts in the project have no knowledge on the principle of value engineering and has no willingness to implement the principle. The evaluation made using value engineering principle shows the current management practice was more conventional and the industry is still facing delay of projects, cost overrun and poor quality while there are opportunities to minimize such problems. VL - 7 IS - 1 ER -