Assessment of Stakeholders Management Protocols with a Special Focus on Selected Joint Projects in Ethiopia

Received: 9 June 2023     Accepted: 29 June 2023     Published: 10 August 2023
Views:       Downloads:
Abstract

The purpose / objective of this study is to provide new theoretical and empirical insights into joint project stakeholder related phenomena through the study of how stakeholders attempt to influence joint projects; and how a joint project management tries to manage these influences in joint multi-firm projects. Accordingly, the focus of this study is the evaluation of the stakeholder management protocol of joint projects performed by selected non-governmental organizations (NGOs) that are recently functioning in Ethiopia. For the reason that the overriding purpose of the study is to investigate the stakeholder management experience of the designated institutions as practiced in the selected projects, this study has made use of descriptive method of research design. In the meanwhile, mixed research approach has been adopted to carry out the study. Moreover, because it was possible to obtain the information the researcher needed from all stakeholders of the designated institutions simultaneously, the time dimension of the study is cross-sectional. The target population of this study is the entire project personnel, the relevant government officials, and project beneficiaries of the chosen projects, out of which 15% is taken as a representative sample. Because the appraisal principally targeted on those individuals who had experiences with project stakeholder management, a non-probability judgment sampling technique was adopted. Finally, the findings of this study highlighted the importance of stakeholder management in joint projects. Through the application of the ideas of stakeholder theory, the results of this study provided new theoretical and empirical understanding of how joint project stakeholders may influence the project management’s decision making during the project lifecycle. These findings also demonstrated how a joint project may analyze its stakeholder environment and respond to stakeholder pressures and unexpected events in the context of joint projects. Ultimately, the new knowledge of joint stakeholders’ influence strategies and better understanding of how a joint project can deal with stakeholder influences supports project managers in the development of effective project stakeholder management approaches.

Published in International Journal of Engineering Management (Volume 7, Issue 2)
DOI 10.11648/j.ijem.20230702.11
Page(s) 15-26
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2023. Published by Science Publishing Group

Keywords

Project Stakeholders, Project Stakeholders Management, Joint Projects, Conflicting Interests

References
[1] Alexander, E. (2010). 'Rationality Revisited: Planning Paradigms in a Post-modernist Perspective'. Journal of Planning, Education and Research, 19, pp 24-2-56.
[2] Berman, S. L., et al. (1999). Does stakeholder orientation matter? The relationship between stakeholder management models and firm financial performance. Academy of management Journal, Mississippi State 42 (5): 488-506.
[3] Bourda, L. (2005). Change management theories and methodologies: The use of change management, CIMA Publishing, United Kingdom.
[4] Cohen, A. and Maroon, V. (1999). Corporate Social Responsibility. International Journal of Management Reviews, 12, pp. 1-7.
[5] Engwall M., (2003). No project is an island: linking projects to history and context. Research Policy, 32 (5), 789-808.
[6] Flyvbjerg B., Bruzelius N., Rothengatter, W., (2003). Megaprojects and Risk: an Anatomy of Ambition, Cambridge University Press, Cambridge.
[7] Grün O., (2004). Taming Giant Projects: Management of Multi-organization Enterprises, Springer, Berlin.
[8] Hummels, H. (1998). Organizing ethics: A stakeholder debate. Journal of Business Ethics, Dordrecht 17 (13): 1403-1419.
[9] Maylor, R. (2010). 'Collaborative Planning: Building Consensus and a Distinct Model of Practice'. Journal of Planning Education and Research, 12 p. 77.
[10] McElroy, B., Mills, C., (2003). Managing Stakeholders. In: Turner, R. J. (Ed.). People in Project Management, Aldershot, Gower, 99–118.
[11] Miller R, & Lessard, D. (2000). The strategic management of large engineering projects: shaping risks, institutions and governance. International Journal of Project Management, pp. 437-443.
[12] Olander, S., & Landin, A. (2005). Evaluation of stakeholder influence in the implementation of construction projects. International Journal of Project Management, 23 (4), 321-328. http://dx.doi.org/10.1016/ j.ijproman.2005.02.002. [Accessed: 13th May, 2017].
[13] Sunderland, J. (2006). The Stakeholder Paradox, Extract from the Henley Partnership Keynote Lecture Series.
[14] Winch, G. M., Bonke S., (2002). Project stakeholder mapping: analyzing the interests of project stakeholders. In: Slevin D. P., Cleland D. I., Pinto J. K., (Eds.), The Frontiers of Project Management Research, Project Management Institute, BA Mills, Newton Square, 385-403.
[15] Yogesh Kumar Singh (2006). Fundamental of Research Methodology and Statistics. Mahatma Gandhi Chitrakoot Rural University, New Age International (P) Limited, Publishers.
Cite This Article
  • APA Style

    Yehualashet Getahun Ayele. (2023). Assessment of Stakeholders Management Protocols with a Special Focus on Selected Joint Projects in Ethiopia. International Journal of Engineering Management, 7(2), 15-26. https://doi.org/10.11648/j.ijem.20230702.11

    Copy | Download

    ACS Style

    Yehualashet Getahun Ayele. Assessment of Stakeholders Management Protocols with a Special Focus on Selected Joint Projects in Ethiopia. Int. J. Eng. Manag. 2023, 7(2), 15-26. doi: 10.11648/j.ijem.20230702.11

    Copy | Download

    AMA Style

    Yehualashet Getahun Ayele. Assessment of Stakeholders Management Protocols with a Special Focus on Selected Joint Projects in Ethiopia. Int J Eng Manag. 2023;7(2):15-26. doi: 10.11648/j.ijem.20230702.11

    Copy | Download

  • @article{10.11648/j.ijem.20230702.11,
      author = {Yehualashet Getahun Ayele},
      title = {Assessment of Stakeholders Management Protocols with a Special Focus on Selected Joint Projects in Ethiopia},
      journal = {International Journal of Engineering Management},
      volume = {7},
      number = {2},
      pages = {15-26},
      doi = {10.11648/j.ijem.20230702.11},
      url = {https://doi.org/10.11648/j.ijem.20230702.11},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ijem.20230702.11},
      abstract = {The purpose / objective of this study is to provide new theoretical and empirical insights into joint project stakeholder related phenomena through the study of how stakeholders attempt to influence joint projects; and how a joint project management tries to manage these influences in joint multi-firm projects. Accordingly, the focus of this study is the evaluation of the stakeholder management protocol of joint projects performed by selected non-governmental organizations (NGOs) that are recently functioning in Ethiopia. For the reason that the overriding purpose of the study is to investigate the stakeholder management experience of the designated institutions as practiced in the selected projects, this study has made use of descriptive method of research design. In the meanwhile, mixed research approach has been adopted to carry out the study. Moreover, because it was possible to obtain the information the researcher needed from all stakeholders of the designated institutions simultaneously, the time dimension of the study is cross-sectional. The target population of this study is the entire project personnel, the relevant government officials, and project beneficiaries of the chosen projects, out of which 15% is taken as a representative sample. Because the appraisal principally targeted on those individuals who had experiences with project stakeholder management, a non-probability judgment sampling technique was adopted. Finally, the findings of this study highlighted the importance of stakeholder management in joint projects. Through the application of the ideas of stakeholder theory, the results of this study provided new theoretical and empirical understanding of how joint project stakeholders may influence the project management’s decision making during the project lifecycle. These findings also demonstrated how a joint project may analyze its stakeholder environment and respond to stakeholder pressures and unexpected events in the context of joint projects. Ultimately, the new knowledge of joint stakeholders’ influence strategies and better understanding of how a joint project can deal with stakeholder influences supports project managers in the development of effective project stakeholder management approaches.},
     year = {2023}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Assessment of Stakeholders Management Protocols with a Special Focus on Selected Joint Projects in Ethiopia
    AU  - Yehualashet Getahun Ayele
    Y1  - 2023/08/10
    PY  - 2023
    N1  - https://doi.org/10.11648/j.ijem.20230702.11
    DO  - 10.11648/j.ijem.20230702.11
    T2  - International Journal of Engineering Management
    JF  - International Journal of Engineering Management
    JO  - International Journal of Engineering Management
    SP  - 15
    EP  - 26
    PB  - Science Publishing Group
    SN  - 2640-1568
    UR  - https://doi.org/10.11648/j.ijem.20230702.11
    AB  - The purpose / objective of this study is to provide new theoretical and empirical insights into joint project stakeholder related phenomena through the study of how stakeholders attempt to influence joint projects; and how a joint project management tries to manage these influences in joint multi-firm projects. Accordingly, the focus of this study is the evaluation of the stakeholder management protocol of joint projects performed by selected non-governmental organizations (NGOs) that are recently functioning in Ethiopia. For the reason that the overriding purpose of the study is to investigate the stakeholder management experience of the designated institutions as practiced in the selected projects, this study has made use of descriptive method of research design. In the meanwhile, mixed research approach has been adopted to carry out the study. Moreover, because it was possible to obtain the information the researcher needed from all stakeholders of the designated institutions simultaneously, the time dimension of the study is cross-sectional. The target population of this study is the entire project personnel, the relevant government officials, and project beneficiaries of the chosen projects, out of which 15% is taken as a representative sample. Because the appraisal principally targeted on those individuals who had experiences with project stakeholder management, a non-probability judgment sampling technique was adopted. Finally, the findings of this study highlighted the importance of stakeholder management in joint projects. Through the application of the ideas of stakeholder theory, the results of this study provided new theoretical and empirical understanding of how joint project stakeholders may influence the project management’s decision making during the project lifecycle. These findings also demonstrated how a joint project may analyze its stakeholder environment and respond to stakeholder pressures and unexpected events in the context of joint projects. Ultimately, the new knowledge of joint stakeholders’ influence strategies and better understanding of how a joint project can deal with stakeholder influences supports project managers in the development of effective project stakeholder management approaches.
    VL  - 7
    IS  - 2
    ER  - 

    Copy | Download

Author Information
  • School of Commerce, Addis Ababa University, Addis Ababa, Ethiopia

  • Sections