Accurate quantification of lost productivity on contractors due to disruption by the Client is one of the major headache in the field of claim analysis. Estimation of lost productivity is one of the contentious task under claim management and very challenging to attain accurate loss in productivity. There are a number of methods provided for estimation of damages caused by lost productivity, but among them Measured Miles method is known for its accuracy and preferred by courts and boards. Measured Mile method works by comparing actual productivities obtained during two different sessions at which the company was exercising its full capacity and those times where the progress of the work was impaired by the Employer. In order to show the procedure employed to conduct a Measured Miles approach to quantify a disruption and prolongation damages a case study a claim occurred at Great Ethiopian Renaissance Dam Project is carried out. Finally, the study shows how much Measured Miles approach is helpful for equitable decision-making and helped the Employer to protect himself from unnecessary expense caused by biased decision.
Published in | Advances in Sciences and Humanities (Volume 6, Issue 4) |
DOI | 10.11648/j.ash.20200604.11 |
Page(s) | 94-100 |
Creative Commons |
This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited. |
Copyright |
Copyright © The Author(s), 2020. Published by Science Publishing Group |
Measured Miles Approach, Disruption, Prolongation, Modified Total Cost
[1] | W. Ibbs and M. Liu, “Improved measured mile analysis technique,” J. Constr. Eng. Manag., vol. 131, no. 12, pp. 1249–1256, 2005, doi: 10.1061/(ASCE)0733-9364(2005)131:12(1249). |
[2] | P. J. Keane and A. F. Caletka, Delay analysis in construction contracts: 2nd edition. Wiley Blackwell, 2015. |
[3] | Andy Hewitt Hewitt, Construction Claims & Responses effective writing & presentation, vol. 1. 2016. |
[4] | E. K. Zaneldin, “Investigating the types, causes and severity of claims in construction projects in the UAE,” International Journal of Construction Management, Taylor and Francis Ltd., 2018. |
[5] | A. Ness, “the Law of Construction Delay, Acceleration & Disruption,” 2010. |
[6] | J. G. Zack, “Delay and Delay Analysis: Isn ’ T It Simple?,” no. December 2005, 2006. |
[7] | M. R. Bin Mohamad, “THE FACTORS AND EFFECT OF DELAY IN GOVERNMENT CONSTRUCTION PROJECT (CASE STUDY IN KUANTAN),” Το Β$Η$Μ$Α$ Το$Υ$ Α$Σ$Κ$Λ$Η$Π$Ι$Ο$Υ$, vol. 9, no. 1, pp. 76–99, 2010, doi: 10.1558/jsrnc.v4il.24. |
[8] | L. C. D. and W. H. P. Nathan Chapman, “Resolving Problems and Disputes on Construction Projects: Tackling Contract Performance Delays | Lorman Education Services,” 2014. |
[9] | R. Gemmel and M. Caswell, “Conquering Concurrency Part 1: What is concurrent delay?,” pp. 1–5, 2018. |
[10] | R. Gibson, Construction Delays: Extensions of Time and Prolongation Claims. 2009. |
[11] | R. J. Gemmell, “The quantification of loss caused by disruption: How applicable is the measured mile method ?,” 2015. |
[12] | levelset.com, “Disruption Claims | Getting Paid for Lost Productivity,” 2019. |
[13] | Gibbs, Kenneth C. Gibbs, and Gordon Hunt, “California Construction Law - Gibbs, Kenneth C. Gibbs, Gordon Hunt - Google Books,” Aspen, 2009. |
[14] | David Chappell, Vincent Powell-Smith, and John H. M. Sims, “Building Contract Claims - David Chappell, Vincent Powell-Smith, John H. M. Sims - Google Books,” Wiley, 2008. |
[15] | Hamish Lal, “Quantifying and Managing Disruption Claims - Hamish Lal - Google Books,” Thomas Telford Publishing, Thomas Telford Ltd, 1 Heron Quay, London E14 4JD. URL://www.thomastelford.com, 2002. |
[16] | Ali Haidar, Global Claims in Construction. Springer-Verlag London Limited, 2011. |
[17] | D. Nelson, “The Analysis and Valuation of Disruption,” no. January, pp. 1–31, 2011. |
[18] | SCL, Society of Construction Law Delay and Disruption 2nd edition February 2017, no. February. 2017. |
[19] | T. Zhao, P. E. Psp, and M. Dungan, “CDR. 1967 Determining the Measured Mile for Lost Productivity Claims,” pp. 1–17, 2015. |
[20] | D. T. KNIGHT, ESQUIRE, and E. SETH M. SCHIMMEL, The Total Cost Method: An alternative theory for provng damage. 1997. |
[21] | J. B. Tieder, “TOTAL COST AND MODIFIED TOTAL COST CLAIMS IN THE UNITED STATES Hotel Concorde La Fayette 3 , Place du General Koenig 2 - 4 May 2013 DRBF 13th Annual International Conference & Training Workshop,” 2013. |
[22] | R. M. Jones, “Update on Proving and Pricing Inefficiency Claims,” Constr. Lawyer, pp. 3–11, 2003. |
[23] | J. G. Zack and P. V. Badala, “Pricing contractor delay costs,” AACE Int. Trans., vol. 2, pp. 876–894, 2012. |
[24] | “Measuring Productivity - OECD Manual,” in Measuring Productivity - OECD Manual, 2001, doi: 10.1787/9789264194519-en. |
[25] | V. S. Zala, “A Study Of Productivity And Financial Efficiency Of Textile Industry Of India”. |
APA Style
Tewodros Goitom. (2020). Estimation of Labour Damage for Disruption and Prolongation Claims Using Measured Miles Analysis. Advances in Sciences and Humanities, 6(4), 94-100. https://doi.org/10.11648/j.ash.20200604.11
ACS Style
Tewodros Goitom. Estimation of Labour Damage for Disruption and Prolongation Claims Using Measured Miles Analysis. Adv. Sci. Humanit. 2020, 6(4), 94-100. doi: 10.11648/j.ash.20200604.11
AMA Style
Tewodros Goitom. Estimation of Labour Damage for Disruption and Prolongation Claims Using Measured Miles Analysis. Adv Sci Humanit. 2020;6(4):94-100. doi: 10.11648/j.ash.20200604.11
@article{10.11648/j.ash.20200604.11, author = {Tewodros Goitom}, title = {Estimation of Labour Damage for Disruption and Prolongation Claims Using Measured Miles Analysis}, journal = {Advances in Sciences and Humanities}, volume = {6}, number = {4}, pages = {94-100}, doi = {10.11648/j.ash.20200604.11}, url = {https://doi.org/10.11648/j.ash.20200604.11}, eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ash.20200604.11}, abstract = {Accurate quantification of lost productivity on contractors due to disruption by the Client is one of the major headache in the field of claim analysis. Estimation of lost productivity is one of the contentious task under claim management and very challenging to attain accurate loss in productivity. There are a number of methods provided for estimation of damages caused by lost productivity, but among them Measured Miles method is known for its accuracy and preferred by courts and boards. Measured Mile method works by comparing actual productivities obtained during two different sessions at which the company was exercising its full capacity and those times where the progress of the work was impaired by the Employer. In order to show the procedure employed to conduct a Measured Miles approach to quantify a disruption and prolongation damages a case study a claim occurred at Great Ethiopian Renaissance Dam Project is carried out. Finally, the study shows how much Measured Miles approach is helpful for equitable decision-making and helped the Employer to protect himself from unnecessary expense caused by biased decision.}, year = {2020} }
TY - JOUR T1 - Estimation of Labour Damage for Disruption and Prolongation Claims Using Measured Miles Analysis AU - Tewodros Goitom Y1 - 2020/11/24 PY - 2020 N1 - https://doi.org/10.11648/j.ash.20200604.11 DO - 10.11648/j.ash.20200604.11 T2 - Advances in Sciences and Humanities JF - Advances in Sciences and Humanities JO - Advances in Sciences and Humanities SP - 94 EP - 100 PB - Science Publishing Group SN - 2472-0984 UR - https://doi.org/10.11648/j.ash.20200604.11 AB - Accurate quantification of lost productivity on contractors due to disruption by the Client is one of the major headache in the field of claim analysis. Estimation of lost productivity is one of the contentious task under claim management and very challenging to attain accurate loss in productivity. There are a number of methods provided for estimation of damages caused by lost productivity, but among them Measured Miles method is known for its accuracy and preferred by courts and boards. Measured Mile method works by comparing actual productivities obtained during two different sessions at which the company was exercising its full capacity and those times where the progress of the work was impaired by the Employer. In order to show the procedure employed to conduct a Measured Miles approach to quantify a disruption and prolongation damages a case study a claim occurred at Great Ethiopian Renaissance Dam Project is carried out. Finally, the study shows how much Measured Miles approach is helpful for equitable decision-making and helped the Employer to protect himself from unnecessary expense caused by biased decision. VL - 6 IS - 4 ER -