Stakeholders Opinion on Selected Effects of Road Construction Delay in the Niger Delta Region of Nigeria

Received: 16 December 2021     Accepted: 17 January 2022     Published: 26 January 2022
Views:       Downloads:
Abstract

Many variables are involved in the construction of road projects. These variables changes with project types and sizes, thus challenging management of these projects to uncertainties. The resulting effects of schedule overrun may be reduced but cannot be completely depleted or eliminated. At these times of scarce and competing resources, critical effects of construction delay are prompted for effective resource deployment in making investment decisions. Eleven important effects of construction delay of road projects awarded by the Niger Delta Development Commission (NDDC) derived from literature and desk file review were identified. These factors which can be linked with stakeholders in the NDDC’s road construction industry i.e., client, contractor, consultant and estate valuer were evaluated by utilising quantitative analysis to get the stakeholder’s opinions on the critical effects from the selected array. Analysis of the questionnaire was also done to assess its statistical significance. To achieve this objectives, exploratory factor analysis (EFA) which includes; Cronbach Alpha Coefficient (CAC) calculation, reliability analysis, multivariate and inferential statistics were employed. The most critical effects of construction delay of road projects awarded by NDDC in the Niger Delta Region of Nigeria are: time overrun, cost overrun, litigation and Disruption to traffic movement. The next critical effects are obstruction of economical and urban movement, total abandonment, dispute, delay of other projects related to the main one, and breach of contract.

Published in American Journal of Environmental Science and Engineering (Volume 6, Issue 1)
DOI 10.11648/j.ajese.20220601.15
Page(s) 30-43
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2022. Published by Science Publishing Group

Keywords

Stakeholders, Construction Delay, Schedule Overrun, Exploratory Factor Analysis, Effects of Construction Delay, Niger Delta Development Commission, Niger Delta Region

References
[1] Owolabi J. D; Amusan, L. M.; Oloke, C. O.; Tunji– Olayemi, P.; Owolabi, D.; Peter, J. and Omuh, I. (2014), “Causes and effect of delay of project construction delivery time”, International Journal of Education and research, Vol. 2, No. 4 April 2014, Pg. 197–208.
[2] Pall, G. K; Bridge, A. J; Skitmore, M. and Gray, J. (2016), “Comprehensive Review of Delays in Power Transmission Projects,” Inst. Eng. Technol., vol. 10, no. 14, pp. 3393–3404.
[3] Khan, L (2015), “Causes of delays in construction projects and their effects” (available at https.//engrligmankhan.wordpress.com), Pg. 1/38-36/38.
[4] Ramli, M. Z; Malek, M. A; Muda, M. Z; Talib, Z. A; Azman, N. S; Fu’ad, N. F. S. M; Zawawi, M. H. and Katman, Y. (2018), A review of Structural Equation Model for Construction Delay Study, International Journal of Engineering & Technology, Vol. 7, pp. 299-306.
[5] Kikwasi, G. J (2012), “Causes and effects of delays and disruptions in construction projects in Tanzania”, Australian Journal of Construction Economics and Building Conference series (2), pp 52-59.
[6] Salunkhe, A. A and Patil, R. S. (2013), “Statistical methods for construction delay analysis”, IOSR Journal of Mechanical and Civil Engineering, Volume 9, Issue 2, Pg. 58–62.
[7] Sunjka, B. P. and Jacob, U. (2013), Significant causes and effects of project delays in the Niger Delta Region of Nigeria, SAIIE25, proceedings Stellenbosch, South Africa, 2013 SAIIE.
[8] Abisuga, A. O; Amusu, O. R. O. and Salvador, K. A. (2014), “Construction delay in Nigeria: A perception of indigenous and multinational construction firms”, Journal of Emerging Trends in Economy and Management Sciences Vol. 3, (5), pp 371–378.
[9] Ogbeide, F. N., Ehiorobo J. O. and Osuji, S. O. (2021a), “Significant Factors Causing Construction Delay of Roads in the Niger Delta Region of Nigeria”, International Journal of Innovative Research in Science, Engineering and Technology (IJIRSET), Vol. 10, Issue 9, September 2021. DOI: 10.15680/IJIRSET:2021.100989.
[10] Ogbeide, F. N., Ehiorobo J. O. and Osuji, S. O. (2021b), “Critical Factors Causing Construction Delay of Roads in the Niger Delta Region of Nigeria”, International Journal of Innovative Research in Science, Engineering and Technology (IJIRSET), Vol. 10, Issue 9, September 2021. DOI: 10.15680/IJIRSET:2021.1009103.
[11] Omatsuli, T (2014), Sustainable Project Management, A paper delivered at the 2014 NDDC Board and Management Retreat, March 12-13, Le Meridian Hotel, Uyo, Nigeria.
[12] Osara, S. I. O (2015), The triad of promoter, engineer and contractor inproject failure, Public Lecture series of the Nigerian Society of Engineers, Benin Branch, April, 30, 275.
[13] Alaghbari, W; Kadir, M. R. A; Salim, A and Ernawati G (2007), “The significant factors causing delay of building construction projects in Malaysia”, Journal of Engineering Construction and Archtechtural Management, Vo1.14 (2), pp. 192-206.
[14] Dinakar, A (2014), “Delay analysis in construction project”, International Journal of emerging technology and advanced engineering, Vol 4 (5), pp 784–788.
[15] Hamzah, N; Khoiry, M. A; Arshada, I., Tawil, N. M., and Che Ani, A. L. (2011), Cause of construction Delay-Theoretical Framework, 2nd International Building Control Conference, Procedia Engineering, Vol. 20, Pp. 490-495.
[16] Alaghbari, W; Saadan, R. S. N; Alaswadi, W and Sultan, B. (2018), Delay factors impacting construction projects in Sana’a-Yemen, PM World Journal, Vol. VII, Issue XII, accessed at www.pmworldjournal.net.
[17] Emeka, O. J (2016), Causes of delay in large building construction project in Nigeria, M. Sc. Dissertation, University of Central Lancashire.
[18] Mohammed, K. A. A. and Isah, A. D. (2012), “Causes of delay in Nigeria construction industry”, Interdisciplinary Journal of contemporary research in Business, Volume 4, No. 2, Pg. 785–794.
[19] Ubani, E. C; Okorocha, K. A and Emeribe, S. C. (2012), “Analysis of factors influencing time and cost overruns on construction projects in South Eastern Nigeria”, International Journal on Management Sciences and Business Research Vol 2, No. 2, Pg. 73-84.
[20] Ibironke, O. T; Oladinrin, T O; Adeniyi, O; and Eboreime, I. V (2013), “Analysis of excusable factors, influencing contractors performance in Lagos State”, Nigeria, Journal of construction in Developing countries, Vol 18 (1), pp 55-72.
[21] Aibinu, A. A. and Jagboro, G. O. (2002); “The effects of construction delays on project delivery in Nigerian Construction industry”, International Journal of Project Management, Vol 20, pp 593-599.
[22] Memon, A. H; Rahman, I. A; Akram, M and Ali, N. M (2014), “Significant factors causing time overrun in construction projects of Peninsular Malaysia”, Journal of modern applied science, Volume 8, Number 4, Pg. 16-28.
[23] Mohamad, M. R. B (2010), The factors and effect of delay in government construction project, case study in Kuantan University, Malaysia, Patiang.
[24] Pourrostam, T and Ismal, A (2011), “Significant factors causing and effects of delays in Iranian Construction Projects”, Australian Journal of Basic and Applied Science, 5 (7), Pg. 450–456.
[25] Koushki, P: Al-Rashid, K and Kartam, N (2005), “Delayed and cost increase in the construction of private residential projects in Kuwait”, Journal of Construction Management and Economics, Vol 20 (3), pp 285-294.
[26] Enshassi, A; Al-Najjar, J and Kumaraswamy, M (2009), “Delays and cost overruns in the construction projects in the Gaza Strip”, Journal of financial and management construction, Vol 14 (2), pp126-151.
[27] Abedi, M; Faith, M. S; and Mohammed, M. F. (2011), Effect of construction delays on construction project objectives, the first Iranian student scientific conference in Malaysia, April 9-10, 2011.
[28] Federal Government of Nigeria (2000), The NDDC Act.
[29] NDDC (2006), Niger Delta Regional Development Master Plan (NDRDMP).
[30] National Population Commission (2004), “GTZ Population Projections on 1991 Census Figures”.
[31] NDDC (2020), Revenue Allocation among NDDC States.
[32] Simon, O. A. and Clinton, A. (2014), Practitioners Perspectives for the Implementation of Sustainable Construction in The Ghanaian Construction Industry, DII-2014 International Conference on Infrastructure Development and Investment strategies for Africa, Livingstone, Zambia. 25-26 September, pg. 114-124.
[33] Kumar, M. Abdul Talib, S. and Ramayah, T. (2013), Business Research Methods, New York: Oxford University press.
[34] Akintoye, A (2000), “Analysis of factors influencing project cost estimating practice”, Construction management and economics, Volume 18 (1), pp. 77-89.
[35] Fellows, R and Liu, A (2008), Research methods for construction, Blackwell Publishing Ltd., UK.
[36] Zhao., Mbachu, J. and Doming, N. (2017), “Exploratory factors influencing building development costs in New Zealand, Building, 7, 57, 16 pages; available at doi: 10,3390/buildings 7030057.
[37] Ogbeide, F. N., Ehiorobo J. O. and Osuji, S. O. (2021d), “Critical Mitigation Strategies for Construction Delay of Roads in the Niger Delta Region of Nigeria”, submitted to the RA Journal of Applied Research, November 2021.
Cite This Article
  • APA Style

    Frederick Nosakhare Ogbeide, Jacob Odeh Ehiorobo, Sylvester Obinna Osuji, Idowu Rudolph Ilaboya. (2022). Stakeholders Opinion on Selected Effects of Road Construction Delay in the Niger Delta Region of Nigeria. American Journal of Environmental Science and Engineering, 6(1), 30-43. https://doi.org/10.11648/j.ajese.20220601.15

    Copy | Download

    ACS Style

    Frederick Nosakhare Ogbeide; Jacob Odeh Ehiorobo; Sylvester Obinna Osuji; Idowu Rudolph Ilaboya. Stakeholders Opinion on Selected Effects of Road Construction Delay in the Niger Delta Region of Nigeria. Am. J. Environ. Sci. Eng. 2022, 6(1), 30-43. doi: 10.11648/j.ajese.20220601.15

    Copy | Download

    AMA Style

    Frederick Nosakhare Ogbeide, Jacob Odeh Ehiorobo, Sylvester Obinna Osuji, Idowu Rudolph Ilaboya. Stakeholders Opinion on Selected Effects of Road Construction Delay in the Niger Delta Region of Nigeria. Am J Environ Sci Eng. 2022;6(1):30-43. doi: 10.11648/j.ajese.20220601.15

    Copy | Download

  • @article{10.11648/j.ajese.20220601.15,
      author = {Frederick Nosakhare Ogbeide and Jacob Odeh Ehiorobo and Sylvester Obinna Osuji and Idowu Rudolph Ilaboya},
      title = {Stakeholders Opinion on Selected Effects of Road Construction Delay in the Niger Delta Region of Nigeria},
      journal = {American Journal of Environmental Science and Engineering},
      volume = {6},
      number = {1},
      pages = {30-43},
      doi = {10.11648/j.ajese.20220601.15},
      url = {https://doi.org/10.11648/j.ajese.20220601.15},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ajese.20220601.15},
      abstract = {Many variables are involved in the construction of road projects. These variables changes with project types and sizes, thus challenging management of these projects to uncertainties. The resulting effects of schedule overrun may be reduced but cannot be completely depleted or eliminated. At these times of scarce and competing resources, critical effects of construction delay are prompted for effective resource deployment in making investment decisions. Eleven important effects of construction delay of road projects awarded by the Niger Delta Development Commission (NDDC) derived from literature and desk file review were identified. These factors which can be linked with stakeholders in the NDDC’s road construction industry i.e., client, contractor, consultant and estate valuer were evaluated by utilising quantitative analysis to get the stakeholder’s opinions on the critical effects from the selected array. Analysis of the questionnaire was also done to assess its statistical significance. To achieve this objectives, exploratory factor analysis (EFA) which includes; Cronbach Alpha Coefficient (CAC) calculation, reliability analysis, multivariate and inferential statistics were employed. The most critical effects of construction delay of road projects awarded by NDDC in the Niger Delta Region of Nigeria are: time overrun, cost overrun, litigation and Disruption to traffic movement. The next critical effects are obstruction of economical and urban movement, total abandonment, dispute, delay of other projects related to the main one, and breach of contract.},
     year = {2022}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Stakeholders Opinion on Selected Effects of Road Construction Delay in the Niger Delta Region of Nigeria
    AU  - Frederick Nosakhare Ogbeide
    AU  - Jacob Odeh Ehiorobo
    AU  - Sylvester Obinna Osuji
    AU  - Idowu Rudolph Ilaboya
    Y1  - 2022/01/26
    PY  - 2022
    N1  - https://doi.org/10.11648/j.ajese.20220601.15
    DO  - 10.11648/j.ajese.20220601.15
    T2  - American Journal of Environmental Science and Engineering
    JF  - American Journal of Environmental Science and Engineering
    JO  - American Journal of Environmental Science and Engineering
    SP  - 30
    EP  - 43
    PB  - Science Publishing Group
    SN  - 2578-7993
    UR  - https://doi.org/10.11648/j.ajese.20220601.15
    AB  - Many variables are involved in the construction of road projects. These variables changes with project types and sizes, thus challenging management of these projects to uncertainties. The resulting effects of schedule overrun may be reduced but cannot be completely depleted or eliminated. At these times of scarce and competing resources, critical effects of construction delay are prompted for effective resource deployment in making investment decisions. Eleven important effects of construction delay of road projects awarded by the Niger Delta Development Commission (NDDC) derived from literature and desk file review were identified. These factors which can be linked with stakeholders in the NDDC’s road construction industry i.e., client, contractor, consultant and estate valuer were evaluated by utilising quantitative analysis to get the stakeholder’s opinions on the critical effects from the selected array. Analysis of the questionnaire was also done to assess its statistical significance. To achieve this objectives, exploratory factor analysis (EFA) which includes; Cronbach Alpha Coefficient (CAC) calculation, reliability analysis, multivariate and inferential statistics were employed. The most critical effects of construction delay of road projects awarded by NDDC in the Niger Delta Region of Nigeria are: time overrun, cost overrun, litigation and Disruption to traffic movement. The next critical effects are obstruction of economical and urban movement, total abandonment, dispute, delay of other projects related to the main one, and breach of contract.
    VL  - 6
    IS  - 1
    ER  - 

    Copy | Download

Author Information
  • Department of Civil Engineering, Faculty of Engineering, University of Benin, Benin City, Nigeria

  • Department of Civil Engineering, Faculty of Engineering, University of Benin, Benin City, Nigeria

  • Department of Civil Engineering, Faculty of Engineering, University of Benin, Benin City, Nigeria

  • Department of Civil Engineering, Faculty of Engineering, University of Benin, Benin City, Nigeria

  • Sections